Go to main Enterprise Ireland site
 
Advanced Search
 
 

 
 
 
Key Messages
How-To Guides
Case Studies
Assessment Tools
Solutions Providers
Library







Vitalograph

5.2 Third Party Selection


Development of the website was undertaken by Limerick based design consultancy Microelectronics Application Centre(MAC). MAC had completed projects for the company previously and Vitalograph were happy with the quality of their work.

Following an initial briefing, MAC responded with a proposal to check they had properly understood the brief. Once this was done, a full proposal with designs was submitted to Gary Casey and the steering committee. MAC built the website infrastructure allowing Vitalograph to add in content themselves. Although MAC could have handled the entire project on an ongoing basis, it was decided that this would be outside the project budget and thus the decision was taken to do this internally.

Research was undertaken by Vitalograph on web hosting companies. The research identified all the potential vendors in Ireland and from there, Host Ireland (www.hostireland.com) was chosen on the basis of having the most flexible package at the best price.

5.3 The Project Team

Internal Team
  • Gary Casey, R&D Manager – Casey held overall responsibility for managing the project and specifying requirements for the website and technical support systems.
  • Shane O’Neill, IT Engineer – O’Neil had hands-on responsibility for IT and ongoing maintenance for the website. He also undertook training and was able then to maintain the website internally without having to incur the costs associated with having an external supplier provide the service.
External Team
  • Des Crosby, MAC – MAC is a part of the University of Limerick. Crosby was responsible for the project management within MAC.
  • Hostireland.com – Provided web hosting services.
5.4 Timeline and Setbacks

The site will go live as this case is being completed, a year after it was handed over to the team in Vitalograph. On handover, the site was set-up on an internal web server but, at that time, lack of staffing internally meant that the team was unable to make the site public. Commented Casey, “There were always more urgent things to be done – we bit off a little more than we could chew”. The development of the site was outsourced to MAC and this lulled the team into a false sense of the level of work required to get the site live. All content had to be written and revised and the site had to be populated with the required information. There was a lot of work after the design was completed. This work may only have taken a full time resource three or four weeks to complete but without that resource, the project took far longer. This development wasn’t a key area of focus and thus often took 2nd place.

5.5 Budget

The project came in on budget from a cost point of view. That said, the amount of man hours involved in the project went over budget by four or five times. “We didn’t fully understand what we were getting into so didn’t realise the amount of effort it would take”, said Casey.

<<<Previous Start of case study Next>>>


National Development Plan The Programmes of Enterprise Ireland are co-funded by EU Structural Funds