|
Sigma
Wireless
6.
Lessons learnt
There were a substantial number of lessons learnt during the implementation
to date of this project.
1. Discovery exercise
As outlined in section 4 once the supplier for the solution
was chosen the discovery exercise was undertaken. This involved
the entire internal and external project team members working through
the requirements and to challenge them from the point of view of
appropriateness and feasibility.
The objective was to develop a realistic and functional set of business
requirements. These were then incorporated into the final business
plan. Both Joseph and Sarann agreed that this part of the process
was critical and saved a lot of time in the future because they
were confident that they had specified a solution that was both
feasible, absolutely appropriate for the business at this point
in time and would scale in line with the developing business strategy.
The final part of the discovery process entailed an extensive internal
communication exercise where the internal project team had to convince
stakeholders, including shareholders, of the business logic behind
the chosen solution. This was particularly important given the decision
had been made not to include a transactional component to the solution.
In that sense the solution was atypical of the prevailing trend
in eBusiness and needed careful explanation. (Although the solution
has been designed to facilitate transactional capability if this
becomes necessary in the future.)
The discipline of the discovery exercise was useful
in ensuring focused thinking and developing a clear business logic
in the alignment between the solution and the business strategy.
2. Treat the project as strategic and give it time
Joseph Moore was clear that you will only receive the return
upon your investment if you give a project sufficient attention
and ensure it is given strategic priority. He said, Everything
that weve invested in, from cross-training, reengineering
our manufacturing processes, our ERP system and now this eBusiness
project, we always get tangible value from it because we give it
the proper time and attention.
3. Experience of ERP implementation
The fact that the project team had only recently been involved
in the successful ERP implementation meant that they were up the
learning curve as a functional working team and were used to dealing
with implementation challenges. This created a confidence to deal
with the challenges of the eBusiness project.
4. Strength and technical ability of team
Most of the suppliers involved in the original tender process
attempted tried to force Sigma Wireless down the package route.
They even went as far as to question whether Sigma Wireless would
be able to implement what they had in mind. However, the team were
clear that an off-the-shelf package could not deliver the functionality
that the business required.
Sarann and Joseph are confident that the technical aptitude of the
team enabled them to be strong and to remain focused on a solution
that was appropriate for the business. If they had been less comfortable
with the technology they admit they may have found it hard to resist
the package route. This would have led to significant limitations
on functionality and the ability of the business to extend the scope
of the operations.
5. Seven months invested in defining requirements
Sarann spent seven months intense work defining the requirements
for the eBusiness solution prior to the development of any architecture
or infrastructure.
Specifically, the following was analysed:
- How
Sigma Wireless currently does business
-
How customers would like to do business
- Defining
the exact parameters of how the eBusiness solution would work
Substantial
work went into profiling different types of customers according
to their information needs. These detailed profiles enable Sigma
Wireless to increase the efficiency of their sales team and to attract
potential customers with appropriate information and marketing messages.
Joseph shared how the ability to efficiently respond to customers
engineering requests has become a key capability for the company.
Joseph and Sarann were clear that the easy part of a project like
this is installing the technology and infrastructure. The hard part
is in ensuring that the business requirements are properly defined.
6. IT teams involvement
Interestingly, the Group IT function only had a limited involvement
during the duration of the project implementation. They became more
seriously involved when the project drew to its end as they were
going to have to take ownership of the new system.
This underlines how the project was driven by the business in line
with and supportive of the new business strategy.
7. Future Plans
Sigma Wireless is currently at the stage where they are populating
the Databank for internal usage. The next stage will involve the
extension of the eBusiness system in two ways.
1. Third parties and suppliers will be brought into the system
to reflect the solution-sell strategy. Sharepoint is
designed to facilitate this expansion in the scope of the business.
2. Customers will be linked in. Private access will be developed
to allow access to certain information. For example, average test
reports. Private access will be secure to ensure that only the appropriate
information can be accessed.
The intention is to develop a push as well as pull
approach to information. Using the customer profiles that have been
established it will be possible to alert customers to particular
information that may be relevant to them and invite them to access
their private workspace.
Note that at this stage there are no plans to develop
a transactional capability via the Web. Joseph is
unconvinced of the business case for this development
at this point in time. The high-touch, low frequency
nature of the customer relationships do not make this
a strategic priority. However, the system has been
designed to enable this functionality if it becomes
important.
|