|
ODonnell
Design
5.2 Third Party Selection
One of the biggest challenges faced by ODonnell
was that of finding the right vendor to implement
the solution. We lost around 6-8 months just
trying to find the right supplier, commented
ODonnell.
Although there were many vendors in the market, many
of them hadnt implemented a system similar to
the one ODonnell was looking for. Although many
vendors claimed they had the experience, when it came
to the crunch, it became apparent that they didnt.
Even once ODonnell thought they had found the
right vendor, trying to get time with them was impossible
this delayed the process considerably, turning
what was a 12 month project into a 24 month project.
It wasnt until half way through the project
that ODonnell came across Tobar, a Cork based
software design house. It was Tobar that eventually
took the bull by the horns and got to work on designing
the shop floor control system. Initially, Tobar took
the Job Specification Sheet (which by this point was
in excel) and transferred it across to Sage. Trakker,
Tobars shop floor data capture system was then
built around that.
ODonnell was also fortunate to have the advice
of an external consultant. Like many SMEs, the advice
of the consultant was invaluable in ensuring that
ODonnell got the best system for its investment.
The advice received empowered ODonnell and allowed
them to meet with vendors with a greater level of
knowledge (rather than arriving at meetings with no
idea as to what could and couldnt be done).
The use of an independent consultant was invaluable
and probably saved us a fortune, said ODonnell.
5.3 The Project Team
5.3.1 Internal Team
The internal team consisted of a number of staff at
ODonnell Design:
- Aodh ODonnell,
Technical Director Aodh was the overall project
manager and had responsibility for ensuring the
project stayed on track.
- Philip
OSullivan, Production Manager Philips
main responsibility was for the shop floor control
system on the factory floor.
- Andrew
Byrnes, CAD Operator/IT Manager Andrew was
employed as a full time CAD operator and is now
also tasked with the ongoing maintenance of the
IT infrastructure.
- Jim ODonnell,
MD Jim oversaw and had full control over
the entire project.
- Peggy
Collins, Accountant Peggy had responsibility
for identifying how each constituent part of the
project affected the accounts side of the business.
- Delwyn
Klevenow - Delwyn had responsibility for sales and marketing including
relationship management with the web developers.
5.3.2
External Team
- Cormac
McCarthy, Tobar Software Cormac worked very
closely with ODonnell Design to implement
Trakker and ensure it integrated with the JSS spreadsheet
that was already in place.
- John
Murphy, DDSI John provided ongoing consultancy
support and advice on what could and couldnt
be done from a technology perspective.
- CCAD
Used as a vendor for CAD software and also
assisted in the installation of some of the network
hardware.
- Deirdre
Souchere, SDTI Deirdre designed and built
the ODonnell Design website.
5.4
Setbacks and difficulties
The biggest issue faced by the team, as discussed earlier, was that of
trying to find the correct software development partner. Once they found
that partner, Tobar Software, much of the project fell into place.
5.5 Budget
ODonnell heavily overspent on some parts of the project but broke-even
or under spent on others. Overall, the project went over budget by around
50% (though more functionality than originally planned was added into
the
specification).
One major issue that hadnt been considered by Aodh ODonnell
was the time-pressure that the project would put him under. All in all,
he had to invest around double the time he thought it would take to implement
the system.
|