Go to main Enterprise Ireland site
 
Advanced Search
 
 

 
 
 
Key Messages
How-To Guides
Case Studies
Assessment Tools
Solutions Providers
Library







Multis Group

5.3 The Project Team


Ongoing maintenance of the internal IT systems is the responsibility of a team of three individuals in the organisation who report into the finance function. Virtually the entire staff was involved in some way in the development and implementation of the new business

system in Multis. There was an overall project manager who oversaw the implementation of the entire system (and relevant team members) in both Ireland and Holland:

Key members of the internal project team included

  • Eric Reed, Financial Director – Eric (Albert Mannion’s predecessor) was responsible for the development and implementation of the eBusiness Strategy. Eric and his team oversaw the entire project from a business viewpoint.
  • Paul Whelan, Project Manager – Paul was responsible for project managing the development and implementation of the business system.
  • Eugene Devaney, Operations and Quality Manager – Eugene had overall responsibility for implementing the business system.
  • Tom Hogan, Sales and Marketing Manager – Tom’s responsibility lay in the implementation of the customer extranet, building links to the relevant digital marketplaces and development of the Multis website.

The external team included consultants from both BSM and Pinnacle:

  • Fiona McCann, Pinnacle Online – Fiona was a project manager within Pinnacle and worked closely with Paul Wheelan on the implementation of the business system. She very quickly understood the idiosyncrasies of the Multis business model and was therefore able to add value very quickly. • Sean Jackson, BSM – Sean led the team in BSM in helping Multis to identify process and requirements and, from there, identify suitable vendors with whom Multis could work to build the required system.
  5.4 Timeline

Driven by the time constraints of the Euro changeover, commercial considerations and the eBusiness Accelerator Fund, the business system was implemented very quickly – in fact, it was one of the quickest installations ever done by Pinnacle Online.

The decision to change the current business system was made in January 2001. Between January and July 2001 an intensive period of planning and preparation was undertaken. Development and implementation of the new system started in July and the system was fully operational by 2nd November, 2001. Additionally, the planning and specification process that Multis had gone through with BSM meant that the team knew what they wanted at the beginning of the implementation and Pinnacle knew exactly what was expected of them.

5.5 Setbacks and difficulties

The early appointment of a project manager was key to the successful implementation of the Multis system and this was highlighted in the time it took to design and implement the system – a little over 4 months. The main difficulty faced by Multis was that of getting the communications infrastructure in place to support the business system across the two sites.

Vendor selection for the VPN was fairly straightforward as there weren’t that many vendors to choose from. A date for installation of the VPN was supplied but there were difficulties in implementing the infrastructure to support the VPN (Local loop & cabling issues). The VPN was promised by October 2001 but wasn’t delivered until Jan 2002 (even though the business system went live in November).

A workaround was put in place to cover the period November to January 2002. Holland dialled in directly to the business system using an ISDN line. This was fine as a workaround and users in Holland received an acceptable performance from the system. This workaround was possible largely because of the thin client capabilities inherent in Sage Enterprise. This solution was only acceptable in the short term as it only supported a limited number of users, had no guaranteed bandwidth was susceptible to security breaches. The VPN was operational by the end of January 2002

5.6 Budget

The eBusiness strategy implemented by Multis represented a significant investment for the company. The actual spend came in under budget mainly due to a saving in capital costs. Multis will be able to use the systems in place as leverage for future growth. For Multis, the system represents an ongoing investment that the company is continually upgrading and investing in to meet the ongoing requirements of its customers and OEMs.

5.7 System Rollout

During the development of the system, Multis closely involved its biggest customers and OEM partners. The team had planned to run the old system in parallel for a period of four weeks. When the new system went live on 2nd November, 2001, it was such a success that the decision was made to turn off the old system after just 7 days. With no extra value being added by its presence there was no good reason to keep it running.

<<<Previous Start of case study Next>>>


National Development Plan The Programmes of Enterprise Ireland are co-funded by EU Structural Funds