|
5.2.1.
IT System Requirements
Hardware
- PC &
Server
- Dell PowerEdge
2500 server
- Dual
PIII 1GHz processor
- 1GB PC133
RAM
- 2 * 18GB
+ 4 * 36GB Hard disks
- MS Small
Business 2000 Server
- Network
- 3COM ISDN
LAN modem
- 3COM
3300 XM switch (24 Port)
Software
- Arcserve
Advanced Back-up software
- Innoclulan
Workgroup Anti-Virus (25 User License)
5.3.
Project Team
The project is still ongoing and having passed through a number of
phases now there has been a number of people and organisations involved
in the implementation.
The internal team has been led by Martin McVicar, the Managing Director.
The project has been managed by Colin Gray, Combilifts IT Manager.
Colins background on the materials side of the business has proved
invaluable. His deep understanding of the business processes and the supply
chain has helped inform the development of the project.
Early in the project Dan Quely from Ernst & Young was employed to
check the quotes and provide an independent, professional opinion. His
expertise was in hardware and, again, it proved invaluable to have a third
party, independent point of view.
The external team included Ernst & Young as discussed earlier. Their
involvement was at the front of the project and they helped drive out
the business requirements for the eBusiness development. Again, Combilift
reiterated the importance of obtaining an independent point of view.
Catseye (www.catseye.ie),
as discussed earlier were the company chosen to design the
new website.
5.4. Project phases
The project broke down into a number of discrete phases. At this point
in time the first two have been implemented and the third phase will be
completed this year.
- Phase
One
This involved networking all of the standalone PCs and installing
a proper back-up system. Prior to this phase most systems werent
backed up at all due to the fact that the PCs were standalone. This
phase was started in July/ August 2001 and was completed by the end
of October 2001.
- Phase
Two
This involved developing the website to draw in more customers
and position the Combilift brand as a solution sell business.
This phase has only recently been completed.
- Phase
Three
This phase will see the development and launch of the Combilift
Extranet. This will enable the dealer network to obtain the information
they require on, for example, spare parts and technical queries.
5.5.
eBusiness Project Benefits
At this point in time the benefits have been concentrated in improved
internal efficiencies as a result of the reduction in departmental overlap
resulting from the networking.
It is too early at this stage to tell but it is hoped that the new website
will result in much increased traffic and leads generated for the dealer
network. Search engine optimisation will be key to success here. The website
will also benefit potential customers by providing sufficient information
for them to make informed choices about short listing suppliers.
Finally, the dealer extranet will benefit the dealers substantially by
saving them time in ordering spare parts, administering the transactions
and in finding out technical information for the product. The extranet
will also benefit Combilift, as it will give them the leverage to continue
to grow the business exponentially.
5.6. Set backs and difficulties
1. Time taken to implement website
Combilift were open about the fact that the website was initially
meant to be up in January but didnt actually get completed until
March. The problem was that it had to go through a number of design changes
before they were entirely happy with it. This related to the fact that
they were not exactly sure what they wanted when they started out on the
project. They admit that the failure to plan properly at the start of
the project probably hindered them in this particular phase of implementation.
|